Project timeline

A timeline of key project phases is below.

November 2025
  • Foundation slab pour.
December 2025
  • framing begins for exterior and roof
  • structural steel grids begin to be installed.

February 2026
  • installation of structural steel grids completed
  • framing completed for exterior, roof, exterior verandah and soffit
  • roof fitted
  • exterior cladding begins.

March 2026
  • interior lining begins
  • carpark construction and landscaping beings
  • installation of aluminium joinery.

April 2026
  • exterior cladding installation completed.

Mid to late 2026
  • interior fit out begins
  • interior lining completed
  • interior fitout completed
  • carpark and landscaping completed.

October 2025
  • Prep for foundation slab
August 2025
  • Construction commences on Tuesday 26 August.
July 2025
  • Recommendation to award construction and civil contract approved by the council.
June 2025
  • Evaluation of pricing completed.
March 2025
  • Design submitted for council approval of tender process
  • Building consent issued.
July to October 2024
  • Contractor appointed for demolition
  • Demolition begins (mid July)
  • Demolition ends (September)
  • Concept design signed off
  • Costings plan and full project timeline completed
  • Resource consent and building consent process begins.
June 2024
  • Tenders close for the contract to demolish the buildings on the site where the new library will be located.
May 2024
  • Design brief confirmed
  • Design team appointed
  • Draft design process is expected to take five months.